Project RTG1001

2 × YHTZ LJMJ4126 轮胎式集装箱门式起重机

Two full-electric rubber tyred gantry cranes for container yard operations — designed, fabricated, assembled and accepted by YHTZ, on schedule from June 2025 to June 2026.

Home / RTG1001 Project
Two YHTZ LJMJ4126 RTG cranes after final assembly
Project Overview

A Flagship Program from Steel Plate to Ship-Set Delivery

Project RTG1001 is YHTZ's flagship RTG program covering the complete lifecycle of two LJMJ4126 rubber tyred gantry cranes: structural fabrication, non-destructive testing, machining, painting, sub-assembly, wharf-side final assembly, factory acceptance and delivery support.

Weekly progress reporting and full-process quality control were applied throughout — every critical weld tracked, every key parameter rechecked — demonstrating exactly how YHTZ serves international customers: transparent schedules, verifiable quality, on-time delivery.

Project No. RTG1001 Model YHTZ LJMJ4126 Quantity: 2 units Start: 19 June 2025 Certificate: 30 June 2026
As-Delivered Data

Product Certificate Highlights产品合格证关键参数

ItemData
ProductRubber Tyred Gantry Crane (RTG) — 轮胎式集装箱门式起重机
ManufacturerYinhai-Tianzhong Cranes (Dalian) Co., Ltd.
Production No.YHTZRTG1001
TypeYHTZ LJMJ4126
Quantity2 units
Rated Capacity41 t
Span26 m
Duty ClassA6
Power Supply380 V / 50 Hz
Factory Certificate Date30 June 2026

Inspection conclusion (per Product Certificate): the products passed factory inspection with qualified safety performance and were approved for delivery. Technical details of the LJMJ4126 design configuration are given on the product page.

Project Journey

From Kick-Off to Delivery项目历程

Milestones documented in the RTG1001 weekly project reports (RTG-ZB series).

June 2025 · 19/06/2025

Project Kick-Off

RTG1001 program officially launched — engineering, procurement and production planning set in motion.

November 2025

Main Structure Fabrication

Left and right side beams assembled and welded (drawing D0371180) with dimensional accuracy on target; groove and weld-path inspections completed before box-structure welding — no rust residue, all dimensions within tolerance.

January 2026

Weld Quality & Precision Assembly

PT (penetrant) inspection of main-beam rail welds passed with zero unqualified defects; trolley-frame weld stress relief performed with JG-T6Y intelligent automatic vibration aging equipment; main beams 3 & 4 assembled to design precision; fourth main-beam cover plate checked for tightness and sealing.

March 2026

Sub-Assembly & Site Entry

Wheel, axle and bogie-beam sub-assembly and hoist assembly in orderly progress; ladder, platform, railing and outrigger painting fully completed with coating quality verified; cables delivered and accepted on site; assembly site entry preparations 100% complete.

May 2026

Final Assembly — 70% and Climbing

All mechanical structures installed at the wharf-side assembly site — trolley traveling system, outriggers, ladders, platforms, railings, trolley and main girders precisely aligned; project fully entered the electrical wiring phase with zero delays or quality deviations.

June 2026 · 30/06/2026

Factory Acceptance & Certificate Issued

Both units passed factory inspection — safety performance qualified and approved for delivery; official Product Certificates issued.

September 2026

Delivery & Commissioning Support

Complete delivery documentation package finalized; on-site commissioning and electrical-installation technical guidance organized for the customer's site operations.

Quality Commitment

Verified at Every Stage全过程质量管控

✓

100% NDT on Critical Welds

PT inspection of main-beam rail welds and trolley-frame welds found no cracks or porosity; key welds on the main structure receive 100% UT examination.

✓

Controlled Stress Relief

Intelligent automatic vibration aging (JG-T6Y) applied to the trolley frame, ensuring long-term structural stability under high-frequency duty.

✓

Precision Assembly Checks

Assembly gaps, fastening torques, alignment accuracy and sealing verified item by item — no deformation, no loose parts, no process violations.

✓

Transparent Weekly Reporting

Bilingual weekly progress reports (RTG Project Weekly Report) with photo evidence kept the customer fully informed from fabrication to acceptance.